Road work: Gilford Road

Posted on Friday, July 28, 2023 03:32 PM

Gilford Road from 20th Sideroad to Beach Road is being rehabilitated and widened. Work includes the installation of a multi-use pathway. 

Construction schedule

The Contractor (Georgian Paving) is scheduled to start on August 7, 2023. Road work is expected to be completed by November 3, 2023. Working hours are anticipated to be between 7 a.m. to 8 p.m. Some work on Saturdays may be required.

Public road access and traffic disruptions

Traffic disruptions may occur during construction. Driveway access...

Road closure: Innisfil Beach Road/Highway 400 Closures

Posted on Wednesday, July 19, 2023 09:43 AM

Update: The Phase 1 closure has been extended to approximately 7 p.m. on July 27.

Innisfil, ON –  The next phase of road closures at Innisfil Beach Road/Highway 400 has been shared with the Town by the Ministry of Transportation.

There will be no access from Highway 400 Northbound to Innisfil Beach Road (IBR) Eastbound or Westbound from July 25 to September 1, 2023. The construction completion date is estimated and subject to change.

Prior to the off-ramps being closed:

  • IBR Westbound and Eastbound...

Road closure: 9th Line (Yonge Street to 20th Sideroad)

Posted on Wednesday, July 12, 2023 04:11 PM

9th Line from Yonge Street to 20th Sideroad will be closed for paving from 7 a.m. to 8 p.m. on July 18-21, 2023. Local traffic only—no through access.

What to expect

Driveway access will be maintained throughout the road closure. Residents on the east side of the rail corridor will have access to their home from 20th Sideroad, while residents on the west side of the rail corridor will have access to their home from Yonge Street. If there are any changes, we will provide notice as soon as possible...

Road closures due to flooding

Posted on Tuesday, June 27, 2023 02:09 PM

Significant rainfall and heavy downpours led to localized flooding in some low-lying areas in Innisfil. All road closures related to the June 27 flooding event have been reopened. 

Innisfil Beach Road, 7th Line, Belle Aire Beach Road, Buchanan Street, Goodfellow Avenue, and Maple Road have been reopened. The main access road within Innisfil Beach Park has also been cleared and the front gate reopened.

Please continue to follow the Town's website or social media for updates. Visit Ontario's website

Construction at the South Innisfil Arboretum

Posted on Tuesday, June 27, 2023 08:40 AM

South Innisfil Arboretum will be temporarily closed due to trail construction beginning July 4, 2023 at 8 a.m. The work is scheduled to be completed by the last week of July 2023, weather permitting.

What to expect

The Town is constructing a two-metre-wide limestone screenings trail at South Innisfil Arboretum and a two-metre-wide asphalt trail connecting the existing Nantyr Drive and Ralston Loop walkways. The trails will conform to AODA standards.