The Town of Innisfil completed the road rehabilitation of Queen Street and Church Street, also known as the "Cookstown Connecting Link", in the fall of 2024. 

Queen Street in Cookstown

Construction details

The construction limits were on Queen Street and Church Street from Cookstown’s west limit (20 metres west of the Home Hardware Building Centre entrance) to Cookstown’s east limit (approximately 280 metres east of Albert Street).

Connecting Link map

The work included:

  • Resurfacing of the road
  • Pavement marking restoration and painting new parking stalls
  • Replacement of some concrete curb and gutter
  • Adjustments to existing maintenance holes and catch basins

Milling and paving work began on September 3, 2024 and was completed by October 28, 2024. 

This project is supported with funding from the Ontario Ministry of Transportation's Connecting Links program

Who do I contact? 

R.J. Burnside & Associates Ltd. is the Contract Administrator for this project. If you have any questions or concerns, please contact one of the team members listed below. 

Town of Innisfil 
Bobbi-Jo Duncan 
Capital Project Manager
Email: bduncan@innisfil.ca
Phone: 705-436-3740 Ext. 3252

R.J. Burnside & Associates Limited
Matthew Kemp, P.Eng.
Contract Administrator
Email: matthew.kemp@rjburnside.com
Phone: 705-797-4380