The contractor will return to pave the top coat of asphalt on Lockhart Road from 20th Sideroad to 25th Sideroad during the week of August 2, 2022, weather dependent. Once the paving is done, the contractor will complete any outstanding work such as driveway tie-ins, shouldering and line painting.

We expect this work to be done by the end of August 2022.

Public road access and traffic disruptions

Here's what residents can expect during construction: 

  • Traffic disruptions
  • One lane closures with traffic control in place
  • Driveway access will be maintained throughout construction, except for temporary disturbances while working in front of driveways. For temporary driveway disturbances, the contractor will advise where to park
  • Loud noise and dust during daytime hours 

Please refrain from parking your car on the road during construction hours between 7:00 a.m. and 7:00 p.m.

Contact us

This project is a partnership between the Town of Innisfil, InnServices and Parkbridge. We thank you in advance for your patience and cooperation. If you have any questions or concerns related to this project, please contact:

Jessie Grewal P.Eng.
Construction Administrator
KiHL Construction Management
416-508-9463

Town of Innisfil Customer Service
705-436-3710
inquiry@innisfil.ca